Jeffrey S. Russell, Ph.D., P.E., Dist.M.ASCE, NAC, F.NSPE
Summary of research grants and contracts
1. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Research in Automation of the Contractor- Prequalification Process July 1989 – July 1990 UW Graduate School $15,000 Research Committee (UW Internal) None 100% |
2. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement:
|
Enhancing the Communication Process between Disadvantaged Business Enterprise Firms and Prime Contractors September 1989 – June 1990 Wisconsin Department of Transportation (DOT) $18,000 Wis DOT-Internal None 100%
|
3. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift May 1990 – August 1990 Wisconsin Road Builders Association $6,000 Wisconsin Road Builders Association- Internal None 100% |
4. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Implementation of the Robotic Logistics Module October 1989 – September 1991 Obayashi Corporation (Subcontracted from Purdue University) $44,000 Obayashi Corporation, Purdue University- Internal None 100% |
5. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Research in an Automated Decision Support for Infrastructure Management July 1990 – July 1991 U.W. Graduate School $2l,611 (P.I. salary portion of $9,222 turned back to Grad- School) Research Committee (U.W. Internal) None 100% |
6. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Evaluation and Quantification of Risks Confronted by Surety Companies Underwriting Reclamation Bonds November 1989 – September 1992 U.S. Department of Interior, Office of Surface Mining Reclamation and Enforcement (Subcontracted from Purdue University) $119,000 National Peer and Expert Panel Review None 100% |
7. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Presidential Young Investigator Award July 1990 – July 1995 National Science Foundation $312,500 National Peer and Expert Panel Review None 100% |
8. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift June – August, 1990 Payne and Dolan, Inc. $30,000 Internal Prof. Steven M. Cramer 50% S. M. Cramer; 50% J. S. Russell |
9. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co – investigator: |
An Analysis and Evaluation of a Plan Quality Evaluation Form September – June 1991 Wisconsin Department of Transportation $25,000 Internal None |
10. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
An Analysis of Constructability Programs November, 1991 – December, 1992 Construction Industry Institute $114,500 Internal None 100% |
11. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift June – August 1990 Wisconsin Concrete Pavement Association $10,000 Internal Prof. Steven M. Cramer 50% S. M. Cramer; 50% J. S. Russell |
12. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift May 1991 – August 1991 Wisconsin Road Builders Association $7,000 Wisconsin Road Builders Association-Internal None 100% |
13. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift August 1991 – December 1991 Wisconsin Road Builders Association $7,500 Wisconsin Road Builders Association-Internal None 100% |
14. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Data Flow Identification to Support Project Automation/Integration and Productivity Improvement July 1992 – July 1993 UW Graduate School $13,500 Research Committee (U.W. Internal) None 100% |
15. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Constructability of Highway Plans: Phase I May 1992 – November 1992 Wisconsin Department of Transportation $10,500 Wisconsin Department of Transportation Internal None 100% |
16. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift May 1992 – August 1992 Wisconsin Road Builders Association $8,000 Wisconsin Road Builders Association-Internal None 100% |
17. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift June – August 1992 James Cape & Sons $10,000 Internal Prof. Steven M. Cramer 50% S. M. Cramer; 50% J. S. Russell |
18. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Analytical Study of Surface Friction of Wisconsin State Trunk Highway System Pavements November 1992 – November 1993 Wisconsin Department of Transportation $59,000 Wisconsin Department of Transportation-Internal Prof. Peter J. Bosscher 75% J.S. Russell; 25% P.J. Bosscher |
19. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Constructability of Highway Plans April 1993 – June 1994 Wisconsin Department of Transportation $88,000 Wisconsin Department of Transportation –Internal None 100% |
20. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Investigation of the Performance of Parting Strips in the Formation of Longitudinal Joints in PCC Pavements May 1993 – May 1994 Wisconsin Department of Transportation $132,000. Wisconsin Department of Transportation-Internal Prof. Awad S. Hanna 50% A. S. Hanna; 50% J. S. Russell; |
21. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Investigation into Vibratory Pile Driving Techniques July 1993 – July 1994 UW Graduate School $7,170 Research Committee (U.W. Internal) None 100% |
22. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Research Experiences for Undergraduates: Construction Engineering and Management July 1992 – June 1993 National Science Foundation $5,000 Internal Review None 100% |
23. |
Project name: Start/end dates: Amount: Review process: Co-investigator: Percent involvement: |
Research Experiences for Undergraduates: Construction Engineering and Management July 1993 – June 1994 $10,000 Internal Review None 100% |
24. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Research Gift Hot Mix Asphalt December 1993 – 2003 Payne and Dolan, Inc. $530,000 Internal Prof. H.U. Bahia 50% H.U. Bahia; 50% J.S. Russell
|
25. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Predicting Bearing Capacity of Piles Installed with Vibratory Drivers AM January 1993 – March 1997 Construction Productivity Advancement Program- U. S. Army Corp of Engineers $500,000 ($155,000 directly received by UW) Expert Panel Prof. Peter J. Bosscher 90% P. J. Bosscher; 10% J.S. Russell |
26. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Predictive Tools for Capital Projects December 1993 – April 1995 Construction Industry Institute $130,620 (responsible for coordination for an additional contract of $25,000 to Professor Edward J. Jaselskis, Iowa State University, thus a total of $155,620). External Review Panel None 100% |
27. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Construction Automation July 1994 – July 1995 UW Graduate School $7,170 Research Committee (U.W. Internal) None 100% |
28. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Asphaltic Pavement Density Comparisons Using Coring and Nuclear Techniques June 1994 – January 1995 Wisconsin Department of Transportation $44,100 WisDOT and Contractor Industry Group Prof. A. S. Hanna 50% A. S. Hanna; 50% J. S. Russell |
29. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Field Validation of SHRP Binder Specification in Wisconsin November 1994 – Jan 1999 Wisconsin Department of Transportation $87,000 WisDOT and Contractor Industry Group Profs. H. U. Bahia and P. J. Bosscher 50% H. U. Bahia; 40% P.J. Bosscher; and 10 % J.S. Russell |
30. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Construction Automation July 1995 – July 1996 UW Graduate School $7,170 Research Committee (U.W. Internal) None 100% |
31. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Asphaltic Pavement Density Comparisons Using Coring and Nuclear Techniques — Phase II June 1995 – January 1996 Wisconsin Department of Transportation $66,000 WisDOT and Contractor Industry Group Prof. A. S. Hanna 50% A. S. Hanna; 50% J.S. Russell |
32. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift May 1995 – August 1995 Wisconsin Road Builders Association $10,000 Wisconsin Road Builders Association-Internal None 100% |
33. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift May 1995 – August 1995 John W. Rogers Foundation $37,500 None None 100% |
34. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Quantification of Impact of Project Change Orders August 1996 – August 1997 National Electric Contractors Association and Mechanical Contractors Association of America $55,000 Peer-reviewed Prof. A.S. Hanna 75% A.S. Hanna; 25% J.S. Russell |
35. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Stacking of Trades on Labor Efficiency. January 1997 – January 1997 National Electric Contractors Association $51,424 Peer-reviewed Prof. A.S. Hanna 75% A.S. Hanna; 25% J.S. Russell |
36. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Development of Constructability Lesson-Learned File June 1996 – June 1997 Wisconsin Department of Transportation $60,000 Internal Prof. A.S. Hanna 50% J.S. Russell; 50% A.S. Hanna |
37. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Unrestricted Research Gift September 1995 – September 1997 Kohler $60,000 None None 100% |
38. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Testing and Inspection Levels for Hot-Mix Asphaltic Concrete (NCHRP 10-39A) February 1996 – February 1998 National Cooperative Highway Research Program Transportation Research Board, National Research Council $260,000 Peer-reviewed Profs. A.S. Hanna and E.V. Nordheim 50% J.S. Russell; 25% A.S. Hanna; and 25% E.V. Nordheim |
39. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Graduate Research Traineeship September 1996 – September 2002 National Science Foundation $562,500 Peer-reviewed Profs. R. Veeramani and T.M. Adams 33% J.S. Russell; 33% T.M. Adams; and 33% R. Veeramani |
40. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Improved Contracting Methods for Highway Construction Projects Amplified Work Plan (NCHRP 10-49) January 1997 – January 1999 National Cooperative Highway Research Program Transportation Research Board, National Research Council Total project $312,500; Subcontract for Texas A&M Univ. $115,000 Peer-reviewed Profs. A.S. Hanna and D. Walker 50% J.S. Russell; 50% A.S. Hanna |
41. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Design and Construction for Maintainability Task Force July 1997 – August 1999 Construction Industry Institute $159,000 External Review Panel None 100% |
42. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
The Use of Gyratory Compaction Results to Predict Optimum Field Compaction September 10, 1997 – September 10, 1998 FHWA $100,000 Internal Profs. H.U. Bahia and P.J. Bosscher 70% H.U. Bahia; 25% P.J. Bosscher; and 5% J.S. Russell |
43. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Design for Maintainability Team January 1997 – November 1999 Construction Industry Institute $125,000 CII internal review of contracted Work None 100% |
44. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Quantifying Impact of Change Orders: A Micro Study – Phase II January 1998 – June 1999 The Electrical Contracting Foundation, Inc. $70,000 Peer-reviewed Prof. A.S. Hanna 75% A.S. Hanna; 25% J.S. Russell |
45. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Quantifying Impact of Change Orders: A Micro Study Phase II January 1, 1998 – January 2, 1999 Mechanical Contractors Association of America $70,000 Internal Prof. A.S. Hanna 75% A.S. Hanna; 25% J.S. Russell |
46. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Cumulative Change Order Impact January 1998 – January 2001 Construction Industry Institute 140,000 CII internal review of contracted Work Awad Hanna 25% |
47. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Development of Constructability Lesson-Learned File September 1998 – August 1999 Wisconsin Department of Transportation $45,000 Internal Prof. A.S. Hanna 50% J.S. Russell; 50% A.S. Hanna |
48. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
University Transportation Center June 1999 – September 2005 U.S. Department of Transportation $890,000 with $890,000 local/state match per year Expert Panel Adams, Wittwer 10% Russell, J.S. |
49. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Track Delamination, Debonding and Deterioration of Bridge Decks by Monitoring Moisture Content and Density of Portland Cement Concrete August 1999 – July 2000 Wisconsin Department of Transportation $10,000 Internal Prof. A.S. Hanna 50% Russell, J.S., 50%Hanna, A.S. |
50. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Project Delivery Systems in the Downstream and Chemical Sector August 1999 – December 2020 Construction Industry Institute $100,000 Expert panel Awad Hanna, Zhenhua Zhu 10% |
51. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Specifications for Fiber Reinforced Plastics February 2000 – May 2002 FHWA $333,333 Internal Bank 50% Bank, L., 40% Georgia Tech, 10% Russell, J.S |
52. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
NCHRP 10-58 Construction Engineering and Management Research Program March 2000 – October 31, 2001 National Academy of Science (NCHRP) $200,000 External Review Process Prof. S. Anderson, Texas A&M University 50% Russell, J.S., 50% Anderson, S. |
53. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Demonstration Bridge Project October 2000 – January 2003 IBRC $500,000 Internal Bank 50% Bank, L., 40% Oliva, M., 10% Russell, J.S. |
54. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
E-commerce Applications to the Construction Industry November 2000 – January 2003 Construction Industry Institute $112,000 Research Committee Veeramani 50% Veeramani; 50% Russell, J.S. |
55. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Innovative Bridge Research and Construction Program 1–Highway 151/Rte. 26 December 2000 – October 2003 FHWA $287,967 Internal Bank and Oliva 10% Russell, J.S. |
56. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Cost Effectiveness of Innovative Crew Scheduling January 2001 – September 2003 Construction Industry Institute $50,000 CII internal review of contracted Work Awad Hanna 10% |
57. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
eCommerce Applications in Construction January 2001 – January 2003 Construction Industry Institute $100,000 CII internal review of contracted Work Raj Veeramani 50% |
58. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Demonstration Bridge Project October 2001 – January 2004 IBRC $500,000 Internal Bank 50% Bank, L; 40% Oliva, M; 10% Russell, J.S. |
59. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Innovative Bridge Research and Construction Program 2 – Highway 151/De Nevue Creek August 2002 – June 2006 FHWA $350,846 Internal Bank 10% Russell, J.S. |
60. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Lessons Learned Database 3.0 September 1, 2002 – August 31, 2003 Wisconsin Department of Transportation $30,000 Internal Hanna 50% Russell, J.S.; 50% Hanna, A. |
61. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Demonstration Bridge Project October 2003 – January 2005 IBRC $350,846 Internal Oliva 50% Bank, L; 40% Oliva, M; 10% Russell, J.S. |
62. |
Project name: Start/end dates: Amount: Review process: Co-investigator: Percent involvement: |
Permeability of Hot Mix Asphalt Pavements November 2002 – November 2005 $225,000 Research Committee Bahia 85% Bahia; 15% Russell, J.S. |
63. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Innovative Bridge Research and Construction Program 4 – USH 12 over Coffee Creek August 2004 – June 2008 FHWA $376,000 Internal Bank 10% Russell, J.S. |
64. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Conceptual Studies for Rapidly Deployable Battlespace Gap Structures – Phase II October 2004 – September 2005 US Army Corps of Engineers $66,246 Internal Bank 10% Russell, J.S. |
65. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Experimental Testing of the Suspension Net Concept Variation September 2005 – September 2006 US Army Corps of Engineers $14,600 Internal Bank 10% Russell, J.S. |
66. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Specification and Design of Fiber Reinforced Bridge Deck Forms for use on Wide Flange T-Girders November 2005 – November 2006 Wisconsin Highway Research Program $94,735 Internal Bank and Oliva 10% Russell, J.S. |
67. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Rapid Bridge Construction Technology – Precast Elements for Substructures October 2006 – October 2008 Wisconsin Highway Research Program $124,411 Internal Oliva and Bank 10% Russell, J.S. |
68. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Lessons Learned 3 November 2006 – December 2009 Wisconsin Dept. of Transportation $272,000 Internal None 100% |
69. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Field Studies May 2007 – January 2008 Wisconsin Dept. of Transportation $16,000 Internal None 100% |
70. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Field Studies May 2008 – August 2008 Wisconsin Dept. of Transportation $14,000 Internal None 100% |
71. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Field Studies June 2008 – September 2008 Wisconsin Dept. of Transportation $10,520 Internal None 100% |
72. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Field Studies June 2008 – May 2009 Wisconsin Dept. of Transportation $27,000 Internal None 100% |
73. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
COE 2010 Project to create a Certificate in Integrated Studies in Science, Engineering, and Society July 2008 – December 2009 College of Engineering $21,000 Internal Sarah Pfatteicher and Daniel Kleinman 30% |
74. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Field Studies June 2009 – May 2010 Wisconsin Dept. of Transportation $37,100 Internal None 100% |
75. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Development of On-Line Classes in Leadership and Sustainability July 2009 – December 2010 College of Engineering $40,000 Internal Alicia Jackson and Pat Eagan 30% |
76. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Quantitative Measurement of Project Manager Competencies November 2012 – November 2014 Construction Industry Institute $241,456 Highly competitive (national) Awad Hanna 25% |
77. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Best Practices for Preventing Out-of-Sequence Construction Activities and Minimizing their Impacts November 2015 – November 2017 Construction Industry Institute $252,915.55 Highly competitive (national) Awad Hanna 25% |
78. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Construction Readiness Assessment for Productivity March 2017 – September 2019 Construction Industry Institute $99,710 CII internal review of contracted work Awad Hanna, Dharmaraj Veeramani 15% |
79. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Project Delivery Contract Strategy Update January 2020 – January 2021 Construction Industry Institute $110,000 CII internal review of contracted work Awad Hanna, Zhenhua Zhu 5% |
80. |
Project name: Start/end dates: Source of funds: Amount: Review process: Co-investigator: Percent involvement: |
Organizational Structures and Processes to Enable Cultivating Change September 2020 – November 2022 Construction Industry Institute $200,000 Expert panel Hala Nassereddine and Joe Labianca from University of Kentucky 10% |